Voir en

français

Winter therapy for the accelerators

Hundreds of people were hard at work during the year-end technical stop as all the accelerators underwent maintenance and upgrade operations

|

Winter therapy for the accelerators

On 12 January, members of the team working on CERN's year-end technical stop prepare to install one of the LHC’s new beam absorbers. The six-metre-long component will be lowered 100 metres into the LHC ring.

When the accelerators are asleep, the technical teams get to work. Since 14 December, no particles have circulated in any part of CERN's accelerator chain, from the particle source to the intermediate rings and the Large Hadron Collider (LHC) itself. The annual year-end technical stop provides an opportunity to carry out maintenance work on equipment and repair any damage as well as to upgrade the machines for the upcoming runs. “We started planning this technical stop as early as June 2015,” says Marzia Bernardini, the leader of the team that organises and coordinates the work. “Hundreds of people from all the technical departments were involved over the course of the 12 weeks."

A long list of maintenance work had to be completed along with important upgrades on all the machines and infrastructures. In the Proton Synchrotron (PS), for example, the third link in the chain, two new items of beam instrumentation equipment have been installed. One ring further along, 16 of the 1818 magnets in the Super Proton Synchrotron (SPS) and its transfer lines to the LHC have been replaced. Since each magnet weighs 16 tonnes, it’s a big job, but one that is performed routinely. The SPS will be 40 this year, and its magnets wear out over time and need to be renovated.

In the LHC, several major operations are under way. Two beam absorbers for injection have been replaced. These huge six-metre-long pieces of equipment are used when the beams are ejected from the SPS and into the LHC: they absorb the SPS beam if a problem occurs, providing vital protection for the LHC. The accelerator’s complex cryogenics system also needs regular maintenance. Two of the LHC’s eight sectors have been emptied of helium, the cooling fluid, to ensure that no losses occur while one of the coldboxes is being repaired. Twelve collimators, on either sides of ATLAS and CMS, have been dismantled ready to be upgraded. These devices protect the machine by absorbing particles that stray from the beam trajectory. Finally, cabling campaigns are continuing throughout the machine: four teams are working in parallel to install 25 km of signal cabling for new equipment and upgrades.

The work affects not only the accelerators but also the experiments, especially the LHC experiments. The collaborations are making the most of the stop to carry out maintenance and upgrades on their detectors, which are made up of millions of components.

The work on the injectors has to be completed by early February and on the LHC and its experiments by early March. The injectors will then be progressively restarted while the LHC magnets are tested, before the arrival of the first beams in the LHC scheduled for the end of March.