TOPIC:

Works at Gate B: closures and access changes on the CERN Meyrin site from August 2026

Written by:

SCE Department

Works at Gate B will result in several periods of full and partial closure between August 2026 and March 2027. Traffic diversions and adjusted opening hours at other entrances to the Meyrin site will be introduced to ensure uninterrupted access to the site throughout the works.

The works will be carried out in several phases. The dates may be subject to minor adjustments, depending on site conditions and construction progress.

PhaseScheduled PeriodImpact
Phase 13 August – 30 August 2026No impact on access
Phase 231 August – 4 October 2026Full closure of Gate B and Route Einstein junction
Phase 35 October – 8 November 2026Full closure of Gate B
Phase 411 November 2026 – 7 February 2027Partial closure of Gate B: open for exit only
Additional closures12-14 February 2027 and 5-7 March 2027Full closure of Gate B for two weekends

Alternative site access arrangements

During the closure periods (31 August 2026 – 7 February 2027), the following arrangements will be in place:

GateOpening hoursAccess
Gate A24/7Light vehicles, pedestrians and cyclists. A CERN guard will be on hand to assist visitors.
Gate CMonday to Friday, 06.00-20.00Light vehicles, pedestrians and cyclists.
Gate EMonday to Friday, 07.00-20.00Two-way access for personnel and contractors.
Gate D07.00-19.00Buses and oversized vehicles. Access outside these hours will be possible by submitting a request to the CERN Access Control Centre (CSA): +41 22 767 6666.
Inter-site tunnelUnchangedAccess restricted to authorised users.

During the partial closure of Phase 4 (11 November 2026 – 7 February 2027), Gate B will remain open for exit only, for vehicles, pedestrians and cyclists.

Traffic, mobility and building access changes

From 31 August 2026, the current bus stop at B300 will be replaced by the stop at B39. The bicycle station currently located near B120 will be relocated to B124. Further information will be communicated in due course.

During Phase 2, the junction between Route Pauli and Route Einstein will be closed. Those travelling between Route Einstein and Route de Meyrin should follow the diversion via Route Democrite and Route Rutherford. Temporary traffic signs will be installed to direct road users.

Access to B55 from Gate B will be unavailable throughout the works. B55 will remain accessible via B56.

Stay informed

For more information, please visit the dedicated page on the SCE Department’s website. Additional information and reminders will be published before each major phase of the works.