Tag: Proton Synchrotron Booster

  • Accelerator Report: Excellent performance at the LHC

    Accelerator Report: Excellent performance at the LHC

    The LHC has successfully reached the nominal performance required for Run 3, marking an important milestone in the 2026 physics programme. It has now entered a special run with a reduced number of collisions per bunch crossing

    Explore →

  • Accelerator Report: Run 3 operations counting down to LS3

    Accelerator Report: Run 3 operations counting down to LS3

    Linac4 and the PS Booster have already completed their standalone beam commissioning successfully and have handed over the baton to the PS

    Explore →

  • Accelerator Report: Good performance for some, swift recovery for others

    Accelerator Report: Good performance for some, swift recovery for others

    The LHC pre-injectors delivered excellent availability throughout recent weeks, while an SPS electrical fault and an LHC collimator vacuum leak have been overcome, allowing a successful return to full luminosity production

    Explore →

  • Accelerator Report:  A summer of hot spells for the LHC

    Accelerator Report: A summer of hot spells for the LHC

    So far the summer run has seen solid progress in luminosity production, but also some unexpected beam and machine behaviour. Careful monitoring revealed a hardware issue, now being closely watched as the LHC continues to perform at full capacity.

    Explore →

  • Particles are back in the accelerators

    Particles are back in the accelerators

    The four accelerators that feed into the Large Hadron Collider have all been restarted, while the LHC itself will receive its first particles in April

    Explore →

  • Accelerator Report: Recommissioning on track as the first beams progress through the complex

    Accelerator Report: Recommissioning on track as the first beams progress through the complex

    The recommissioning of the accelerators is progressing according to schedule. Unsurprisingly, some issues have arisen, but they have been swiftly addressed by equipment experts. First physics in the PS East Area and n_TOF is scheduled to start next week

    Explore →

  • Accelerator Report: Linac4 beam commissioning is nearing completion and the PS Booster is next in line

    Accelerator Report: Linac4 beam commissioning is nearing completion and the PS Booster is next in line

    While the first H⁻ ion beams have been accelerated up to 160 MeV in Linac4, the PS Booster is preparing for its first proton injection of 2025

    Explore →

  • Accelerator Report: Another exciting year ahead

    Accelerator Report: Another exciting year ahead

    Although the much-appreciated winter break is well behind us and most of us are back at work, the accelerator complex is still in hibernation – but not for much longer

    Explore →

  • Accelerator Report: A well-deserved winter break for the accelerator complex

    Accelerator Report: A well-deserved winter break for the accelerator complex

    Soon, CERN personnel will take a well-deserved winter break, just like the accelerator complex. Following a successful year, the remainder of the accelerator complex was stopped on 2 December, marking the official start of the year-end technical stop

    Explore →

  • Accelerator Report: No summer holidays for the accelerator complex

    Accelerator Report: No summer holidays for the accelerator complex

    CERN’s accelerators show very good availability rates: beams are in place

    Explore →