On 11 May, four days before the original schedule had set a target of 1200 bunches per beam, the LHC made its final intensity ramp-up step to 2400 bunches per beam
The beam commissioning of the Antiproton Decelerator will start on 12 June, and the aim is to deliver antiprotons to the eagerly waiting AD-ELENA experiments on 30 June
Another important milestone was achieved in the LHC beam commissioning: on 21 April, the LHC Engineer in Charge declared “stable beams” at 6.8 TeV, the first time in 2023
The successful replacement of a coil in an HL-LHC niobium–tin quadrupole magnet by the US Accelerator Upgrade Project team has showcased this crucial technology’s flexibility and cost-effectiveness
Following the installation of kicker magnets that are more heat resistant and their successful tests during the SPS scrubbing run, the SPS is getting ready for High-Luminosity LHC operation.
With the progressive recommissioning of the injectors – including, now, the SPS – the various types of beam are being set up and are gradually reaching the downstream accelerators